HS2 is the UK’s biggest infrastructure project, which is supposed to transform public transport between London, the Midlands and the North.
But it is becoming synonymous with disappointment, delays and an enormous bill.
It’s been backed by more than one government and political party, with prime minister Boris Johnson signalling it could go ahead yet again in February 2020, despite concerns over spiralling costs.
Given the latest government announcement that parts of the line will be delayed, though, will HS2 ever reach its intended destination?
What is HS2?
HS2 is a planned high-speed rail network which was initially intended to link London and the West Midlands, with a further phase extending to cities in the North.
It was first mooted by the Labour government in 2009.
The project has been beset by delays and rising costs, with some estimates now putting the price tag at more than £100bn.
The original bill – at 2009 prices – was supposed to be £37.5bn.
It could be the 2040s before passenger services are operating on the full network.
Be the first to get Breaking News
Install the Sky News app for free
New stations and 18 trains an hour
HS2’s inception follows the development of HS1, the high-speed line between London and Kent connecting the UK to routes on the European continent.
The aim is to run 18 trains an hour in each direction to and from London – at speeds of up to 224mph – compared to between two and six an hour on Europe’s high-speed railways.
It involves the construction of more than 300 bridges and 70 viaducts for the London-West Midlands phase alone.
There will also, under current plans, be new stations – including Birmingham Curzon Street and extensions for London Euston and Manchester Piccadilly.
The project is designed to meet the long-term growth in demand for rail services, improve the reliability of the network, boost connectivity by making journeys faster and easier, and help economic growth across the UK.
Please use Chrome browser for a more accessible video player
What is the route?
Stations on the first phase of the line will be London Euston, Old Oak Common in west London, Birmingham interchange and Birmingham Curzon Street.
The second phase will see trains head northwest to Manchester Airport and Manchester Piccadilly, or use existing lines via Wigan, Crewe and Stafford.
The route had also been planned to go northeast from Birmingham towards the East Midlands Hub at Toton.
From there, the trains would continue on the HS2 line to Leeds, with others diverging onto existing lines via Chesterfield and York.
But that eastern extension was scrapped.
And the government has now delayed the Crewe-northwest section by two years.
Where did it all begin?
In 2009, under Labour transport secretary Geoff Hoon, the government set up a company, HS2 Ltd, to look at proposals for a new high-speed line.
The following year, the Department for Transport (DfT) set out plans for a Y-shaped network connecting London and the cities in the North.
Later, under the Conservative-Liberal Democrat coalition, it was confirmed that the line would be built in two phases.
Phase 1 would run from London to the West Midlands, beginning in 2026.
Phase 2, extending from the West Midlands to cities in the North, would start in 2032-33.
Why is HS2 so behind schedule?
By July 2019, the government accepted that timetable was no longer feasible.
Reasons for the delay included a year spent revising cost and schedule estimates for Phase 1 and more time being needed for construction at various sites.
In August 2019, the government announced an independent review of the programme to advise on whether to proceed.
And on Thursday the government announced the construction of sections of HS2 will be delayed by two years to save money.
The COVID-19 pandemic probably didn’t help with progress, either.
What is the latest timetable?
Delays will affect the northwest section of HS2, from Birmingham to Crewe, and then from Crewe to Manchester.
The first part was due for extension between 2030 and 2034 to help boost transport in the north of England, but the window has now shifted from 2032 to 2036.
Services will not extend to Manchester until the 2040s.
In a written ministerial statement, Transport Secretary Mark Harper said the government is “prioritising HS2’s initial services” between Old Oak Common in west London and Birmingham Curzon Street.
How much is it going to cost?
At the time of the 2010 election, estimates of the cost of HS2 ranged upwards of £20bn.
By January 2012, when the broad route of the proposed scheme was in place, this had risen to £32.6bn.
In June 2013, the coalition government increased the overall cost to £42.6bn and in November 2015, when the figures were updated, in line with inflation, to £55.7bn.
The Department for Transport’s latest estimate in 2021 had spiralled even higher, to between £72bn and £98bn.
But Lord Berkeley, former deputy chairman of the government’s independent review into the project, said it could climb to £107bn.
On Thursday there was a suggestion from Mr Harper that there will be delays in delivering services to central London.
“We will address affordability pressures to ensure the overall spending profile is manageable,” he said.
“We will therefore take the time to ensure we have an affordable and deliverable station design, delivering Euston alongside high-speed infrastructure to Manchester.”
This means it could be more than a decade before high-speed services stop at Euston, with passengers expected instead to travel for half an hour on the Elizabeth Line.
Why have the costs risen so much?
In one word: inflation.
Mr Harper said on Thursday: “We have seen significant inflationary pressure and increased project costs, and so we will rephase construction by two years, with an aim to deliver high-speed services to Crewe and the North West as soon as possible after accounting for the delay in construction.”
But the Confederation of British Industry (CBI) said the delay would hit confidence in the rail industry and could lead to higher overall costs for HS2.
John Foster, the CBI’s policy unit programme director, said: “Delays to projects may create short-term savings, but they can ultimately lead to higher overall costs and slow down the UK’s transition to a better, faster and greener transport network.”
A report in January 2020 by the National Audit Office (NAO) – the spending watchdog – said HS2 Ltd had not accounted for the level of uncertainty and risk in the plans.
It used a method for calculating how much extra might be needed “that was not appropriate for a programme at such an early stage of development”.
Among the factors causing higher costs were commitments to increase the length of tunnelling and to erect noise barriers.
The NAO said the government and HS2 Ltd had “not adequately managed risks to taxpayer money”.
More money was needed for building bridges, tunnels and stations than first thought.
Complex issues involving the discovery of asbestos and archaeological remains, and the need to divert more gas and power lines than expected, have caused problems too.
Please use Chrome browser for a more accessible video player
More money was also needed to buy properties to make way for the rail line.
Even after these have been accounted for, there is uncertainty around the cost of extending London’s Euston station to accommodate the high-speed trains.
Estimated costs for Phase 1 of HS2 alone rose to £35 to £45bn by the latest estimate in late 2021.